Client: Thames Water

Beckton STW, Odour abatement systems

Project Description

Design, Supply and Installation of three large odour abatement systems and extensions to an existing abatement system at Beckton Sewage Works – the largest of its kind in Europe.

System 1 – Inlet Works

Biofilter/Twin CuCarb system to covers (installed by others) with duty/standby fans and all associated ductwork and instrumentation.

Maximum odour output: 1000OUᵋ/mᵌ from 26500mᵌ/hr throughput of air.

System 2 – Storm Overflow

Biofilter/Twin CuCarb system along with duty/standby fans and all associated ductwork and instrumentation.

Maximum odour output: 1000OU/mᵌ from 5500mᵌ/hr throughput of air.

System 3 – PST Feed channels

Biofilter/Twin CuCarb system along with duty/standby fans and all associated ductwork and instrumentation.

Maximum odour output: 1000OUᵋ/mᵌ from 8500mᵌ/hr throughput of air.

OSIL Scope

Turnkey Design, Supply & Installation of three OSIL Lavarok® and CuCarb® odour control systems,  including fans, and interconnecting ductwork, as well as extensions to the existing ductwork to incorporate flow from extension to the Raw Sludge facility.

Project Duration: 28 months