Client: Barhale Trant Utilities, Southern Water

Horsham Water Treatment Works

Odour Mitigation System

Project Description

ChemKlean® odour control system including twin CuCarb® system along with duty/standby fans, chemical dosing pumps & controllers, chemical storage tanks & instrumentation, chemical fill point panel and all associated ductwork and instrumentation treating 4 areas with a total extraction rate of 26,687 mᶟ/h from 55 extraction points.

• Return liquors area

• PST area

• Dewatering Building

• Inlet Works

The systems utilise differing technologies to achieve a level of 99.5% removal of hydrogen sulphide to give a maximum discharge of 1,000 OU/m³ at stack exhaust.

OSIL Scope

Turnkey design, manufacture, supply, installation and commissioning of OSIL ChemKlean® odour control system including fans, ducting, dosing system, electrical panels and chemical bulk storage tanks.

Project Duration: 52 weeks